NEW QUESTION # 28
What happens when you set up detailed scheduling with the finite scheduling mode Insert Operation?
- A. To create a slot, neighbouring operations are moved in both planning directions.
- B. Sequencing on multi-activity resources is automatically updated during planning.
- C. Operations on multi-resources are planned finitely in a sequence.
- D. An operation is scheduled as close as possible to the desired date.
Answer: D
NEW QUESTION # 29
What does the material type influence?
Note: There are 2 correct answers to this question.
- A. Whether value changes to financial accounting stock accounts are updated
- B. Which number range interval the material number comes from
- C. Which plant-specific and plant-independent statuses are allowed
- D. Which document types and class categories are allowed
Answer: A,B
NEW QUESTION # 30
Where do you maintain the work center that represents the production line for repetitive manufacturing? Note: There are 2 correct answers to this question.
- A. Routing
- B. Production cost collector
- C. Production version
- D. Repetitive manufacturing profile
Answer: A,C
NEW QUESTION # 31
For a production version to be valid consistent what requirements must be fulfilled? Note: There are 3 correct answers to this question.
- A. The lot size range must be within the lot size range of the assigned routing.
- B. The consistency check must be performed.
- C. The deletion flag must NOT be set for the bill of material (BOM) or the routing.
- D. The assigned routing bill of material (BOM) must have the same validity period.
- E. The assigned routing bill of material (BOM) must be valid in the entire validity period.
Answer: A,C,E
NEW QUESTION # 32
Mode selection is one of the scheduling options available with Advanced Planning in SAP S/4HANA Cloud Private Edition. When can you use mode selection?
- A. When multiple planned orders are scheduled in parallel on one resource
- B. When alternative resources are used within one operation
- C. When several production versions are maintained for one product
- D. When several operations are maintained for one product
Answer: B
NEW QUESTION # 33
Which chart types does the tabular planning table for capacity planning provide in SAP S/4HANA Cloud Private Edition?
Note: There are 2 correct answers to this question.
- A. Capacity requirements chart
- B. Order (pool) chart
- C. Orders (dispatched) chart
- D. Work center capacities chart
Answer: A,D
NEW QUESTION # 34
You want to set up a maketoorder planning scenario for a finished product. The bill of material contains two components: one should be procured for eac sales order individually the other should be procured jointly for all independent requirements. Forecasting for the finished product is NOT possible. Which settings do you make to achieve this?
- A. Choose planning strategy 20 (MaketoOrder) select the corresponding Individual/Collective indicator.
- B. Choose planning strategy 50 (Planning without final assembly) select the corresponding Individual/Collective indicator.
- C. Choose planning strategy 20 (MaketoOrder) select the corresponding Mixed MRP indicator.
- D. Choose planning strategy 50 (Planning without final assembly) select the corresponding Mixed MRP indicator.
Answer: A
NEW QUESTION # 35
Which of the following are scheduling time elements for a production order?
Note: There are 3 correct answers to this question.
- A. Load time
- B. Float before production
- C. Queue time
- D. Setup time
- E. Transit time
Answer: B,C,D
NEW QUESTION # 36
Which order type is used for repetitive manufacturing?
- A. Kanban order
- B. Process order
- C. Production order
- D. Planned order
Answer: D
NEW QUESTION # 37
You use the Finite Scheduling - with Reverse planning strategy and want to allow scheduling in the past.
How can you parameterize this in the strategy profile?
- A. Specify a negative PP/DS horizon
- B. Specify a negative planning horizon
- C. Specify a negative offset time
- D. Specify a negative opening period
Answer: C
NEW QUESTION # 38
Which chart types does the tabular planning table for capacity planning provide in SAP S/4HANA Cloud Private Edition?
Note: There are 2 correct answers to this question.
- A. Capacity requirements chart
- B. Order (dispatched) chart
- C. Order (pool) chart
- D. Work center capacities chart
Answer: A,D
NEW QUESTION # 39
Which options do you have to plan both quantities capacities during line loading in repetitive manufacturing? Note: There are 2 correct answers to this question.
- A. Run MRP with quota arrangement.
- B. Assign planned orders manually in the planning table.
- C. Run MRP with automatic selection of production version.
- D. Run PP/DS heuristics for repetitive manufacturing.
Answer: A,D
NEW QUESTION # 40
In the context of the capacity scheduling table, how do you define a pacemaker work center?
- A. By assigning it to the first operation of a routing
- B. By assigning it to the bottleneck operation
- C. By assigning it to the production version
- D. By assigning it to the capacity scheduling table
Answer: C
NEW QUESTION # 41
What are prerequisites for a production version to be selected for a production order? Note: There are 3 correct answers to this question.
- A. The basic start date of the order must lie within the validity period of the production version.
- B. The production version must NOT be deleted.
- C. The production quantity must only lie within the lot-size range of the routing in the production version.
- D. The production quantity must lie within the lot-size range of the production version.
- E. The basic end date of the order must lie within the validity period of the production version.
Answer: A,C,D
NEW QUESTION # 42
What is a work center hierarchy?
- A. A group of alternative work centers for production structured in hierarchy levels by priorities
- B. A group of work centers in a production line being used in sequence for production
- C. A group of alternative work centers providing a cumulative available capacity for production
- D. A group of work centers in a parallel sequence that is used to split production quantities work on them in parallel
Answer: C
NEW QUESTION # 43
......