Perfect Oracle EBS R12: Advanced Supply Chain Planning practice exam questions made by Professional group
We have always been attempting to help users getting undesirable results all the time. That is the reason why we invited a group of professional experts who dedicate to the most effective and accurate 1Z0-244 test questions: Oracle EBS R12: Advanced Supply Chain Planning for you. To sort out the most useful and brand-new contents, they have been keeping close eye on trend of the time in related area, so you will never be disappointed about our 1Z0-244 training online questions once you make your order. And you can absolutely get the desirable outcomes. They not only compile the most effective 1Z0-244 original questions for you, but update the contents with the development of society in related area, and we will send the new content about the Oracle 1Z0-244 exam to you for one year freely after purchase.
Three versions of Oracle EBS R12: Advanced Supply Chain Planning exam bootcamp for better study
There are three versions of 1Z0-244 test questions: Oracle EBS R12: Advanced Supply Chain Planning for now with high accuracy and high quality. All these versions of 1Z0-244 training online questions include the key point information that you need to know to pass the test. We will give you some more details of three versions, and all of them were designed for your Oracle 1Z0-244 exam: PDF version-Legible to read and remember, support customers' printing request. Software version- It support simulation test system, and several times of setup with no restriction. Remember support Windows system users only. Oracle 1Z0-244 App online version- Be suitable to all kinds of equipment or digital devices. Be supportive to offline exercise on the condition that you practice it without mobile data. So our three versions of Oracle EBS R12: Advanced Supply Chain Planning exam simulation questions can make different buyers satisfying.
Nowadays, a mass of materials about the Oracle exam flooded into the market and made the exam candidates get confused to make their choice, and you may be one of them. With the high quality and high passing rate of our 1Z0-244 test questions: Oracle EBS R12: Advanced Supply Chain Planning, we promised that our 1Z0-244 training online questions are the best for your reference. So it is a well advised action to choose our materials. Now please take a thorough look about the features of the 1Z0-244 original questions as follow and you will trust our products, so does our services.
Aftersales service 24/7
We have a group of ardent employees who are aiming to offer considerable amount of services for customers 24/7. We are not only assured about the quality of our 1Z0-244 test questions: Oracle EBS R12: Advanced Supply Chain Planning, but confident about the services as well. So we have been trying with a will to strengthen our ability to help you as soon as possible. Our 1Z0-244 original questions speak louder than words, if you have any other questions about our 1Z0-244 training online materials, contact with us and we will solve them for you with respect and great manner. At latest, you can absolutely pass exam with you indomitable determination and our 1Z0-244 test questions: Oracle EBS R12: Advanced Supply Chain Planning.
After purchase, Instant Download 1Z0-244 Dumps: Upon successful payment, Our systems will automatically send the product you have purchased to your mailbox by email. (If not received within 12 hours, please contact us. Note: don't forget to check your spam.)
Oracle EBS R12: Advanced Supply Chain Planning Sample Questions:
1. Exhibit.
In a manufacturing environment where Oracle Shop Floor Management Is used, the production process with Information about Yield (Yld), Net Planning Percent (NPP), Cumulative yield (CY), Reverse Cumulative Yield (RCY) is displayed for a product.
If the order quantity is 100, what is the raw material quantity and resource requirement ASCP will schedule respectively at operation sequence 10?
A) Raw material qty 97.37 and resource requirement for 117.63
B) Raw material qty 98 and resource requirement for 98
C) Raw material qty 113.63 and resource requirement for 113.63
D) Raw material qty 100 and resource requirement for 100
E) Raw material qty 117.63 and resource requirement for 113.63
2. Company ABC Is a computer peripherals manufacturer. They have repetitive manufacturing environment and ate currently using Oracle 11.0.3 products with Supply Chain Planning.
Recently they acquired some companies that have manufacturing units globally. The demand for their products have Increased, which has lead to capacity constraints.
They are considering to Implement/Oracle R12 with Advanced Supply Chain Planning.
Identify the best option.
A) Implement Shopfloor Management and ASCP with Capacity Constrained Plans.
B) Implement Flow Manufacturing and ASCP with Capacity Constrained Plans.
C) Implement Repetitive manufacturing and ASCP with Capacity Constrained Plans.
D) Implement Repetitive manufacturing and keep the existing Supply Chain Planning.
3. Your client has a demand to be satisfied in the future. The plan is a constrained plan, and the Enforce Demand Due Dates check box Is enabled. The plan Issued a supply order to satisfy the above demand with the insufficient lead time exception message. The planning engine compressed the lead times for two of the machine resources to meet the demand due date. There are no other supply orders that have the same exception message.
Your client has the following requirements:
1) The processing times of any operation cannot be compressed.
2) There are no additional machine resources to use.
3) The customer for the above order is willing to receive the order within the minimal possible late days.
Identify the best option in the above scenario.
A) Buy new additional resources.
B) Run a constrained plan with the capacity constrained option enabled.
C) Run the same plan and change the default value of the MSO: Lead Time Control profile option.
D) Run an unconstrained plan.
E) Firm the work order.
4. Identify three correct statements about Shipping Networks.
A) If Intransit inventory is selected, the material Is moved to Intransit Inventory before it reaches the destination Organization In an Inter-Organization transfer.
B) Shipping Networks can also be used to define the relationship between two subinventories in two different Organizations.
C) Organization Access does not restrict users from defining Shipping Networks for Organizations that the user cannot access.
D) You would use the Shipping Network window to define accounting information and the relationships that exist between shipping and destination Organizations.
E) For each Organization relationship that is defined, you must Indicate the type of shipment that is being used.
F) You would define a relationship between two Items that are restricted to subinventories during Item definition.
5. Identify two correct product aggregation levels available In ASCP.
A) Forecast
B) Organization
C) Item
D) Departments
E) Product Family
F) Sales Orders
G) Category
Solutions: